| PHASE | DESCRIPTION | PLAN START | ACT START | PLAN END | ACT END | COMMENTS |
|---|---|---|---|---|---|---|
| 1 | Build Basement (and house). | JUN 2004 | JUN 2004 | MAR 2005 | JUN 2005 | None |
| 2 | Prepare new basement and move old NYS in from storage. Paint basic backdrop (sky) and cove corners. Build Model Shop work bench. | MAY 2005 | JUN 2005 | JUL 2005 | OCT 2005 | Many delays associated with moving into a new house, retiring, etc. |
| 3 | Build basic benchwork and all sub-roadbed for staging level. | OCT 2005 | NOV 2005 | MAR 2006 | MAY 2006 | |
| 4 | Lay trackage and test for staging level. | APR 2006 | AUG 2006 | DEC 2006 | DEC 2007 | |
| 5 | Complete all wiring for staging and pre-wire for main level. Test staging operation and start automation experiments. | SEP 2006 | DEC 2006 | DEC 2007 | FEB 2008 | Electrical testing and automation script development will continue indefinately for now |
| 6 | Build 2nd Level, lay Visible level trackage and begin scenery construction. | JAN 2007 | FEB 2008 |
* Electrical testing and automation scripting will continue indefinately for now.